Works are underway to replace the ceiling of the Driveway Portico at St Luke’s.  

This may affect access to the front door of the building.  If the front door is fenced off, entry to the building will be either from the Courtyard at the rear of the building, or from the Eastern Foyer door – accessible through the Green fence gate to the left of the front of the building.
 
The plan for the works is as follows:
 
  • Friday 5th March – Electrician to remove existing lights
  • Tuesday 9th March – Install temporary barricade and remove existing asbestos ceiling and battens
  • Wednesday 10th March – Start installation of new ceiling
  • Monday 22nd March – Painter to start prep and painting ceiling
  • Thursday 25th March – Electrician to refit lights
  • Friday 26th March – Handover completed works 